ENTSOG GRIP SC 2017-2026 / Annex B - Project Information
Current TYNDP : TYNDP 2017 - Annex A
Page 32 of 620
Interconnector Greece-Bulgaria (IGB Project)
TRA-F-378 Update Date
Project
Pipeline including CS
FID
Advanced
06/05/2016
Construction of a bi-directional gas interconnector between the high pressure natural gas systems of Greece and Bulgaria with a technical forward capacity of 3bcm/y, capable to be increased to 5 bcm/y with the installation of a Compressor Station The current market test is conducted under guidelines and notice approved and issued by the National Regulatory Authorities in accordance to art. 36 of the 2009/73/EC gas directive: RAE decision No.438/23.11.2015 , EWRC decision No.y-2/27.11.2015 : “Updated Guidelines for management and allocation of capacity on the IGB INTERCONNECTOR according to paragraph 6 of article 36 of Directive 2009/73/EC – PHASE I: Invitation of interested parties to express their interest in reserving capacity). RAE decision No.472/1.12.2015, EWRC decision No.y-3/10.12.2015): "EoI Notice"
Description
Regulatory Decisions and similar material conditions
Capacity Increments Variant For Modelling Point
Operator ICGB a.d.
Year 2018
From Gas System To Gas System Capacity
90.0 GWh/d
GR/TAP
BG/IGB
Comment: Initial capacity of 3 bcm/y
Komotini - TAP / IGB
60.5 GWh/d
ICGB a.d.
2021
GR/TAP
BG/IGB
Comment: Added by ENTSOG to match the exit at Stara Zagora
90.0 GWh/d
ICGB a.d.
2018
IB-GRk
BG/IGB
Comment: Increment could also be done in correlation with DESFA
60.5 GWh/d
ICGB a.d.
2021
IB-GRk
BG/IGB
Komotini (DESFA) - GR / IGB
Comment: With relevant committmens from the market and necessary upgrades in the TSOs to be interconnected with IGB, the IGB transportation capacity could be increased from up to 3bcm/y to up to 5 bcm/y forward capacity by installing a Compressor Station.
90.0 GWh/d
ICGB a.d.
2018
BG/IGB
BGn
Comment: Initial capacity of 3 bcm/y
60.5 GWh/d
ICGB a.d.
2021
BG/IGB
BGn
Stara Zagora - IGB / BG
Comment: With relevant committmens from the market and necessary upgrades in the TSOs to be interconnected with IGB, the IGB transportation capacity could be increased from up to 3bcm/y to up to 5 bcm/y forward capacity by installing a Compressor Station.
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Southern Corridor GRIP 2017–2026 Annex B |
48
Made with FlippingBook - Online catalogs