ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 18 of 620

Interconnection Bulgaria - Serbia

TRA-F-137 Update Date

Project

Pipeline including CS

FID

Advanced

27/05/2016

IBS aims at connecting the national gas transmission networks of Bulgaria and Serbia. It will be implemented in 3 stages. 1st: a pipe will be built from Novi Iskar to Kalotina, BG (62.2 km) and from Nis to Dimitrovgrad, SR (108 km), with capacity from BG to SRB - 1,0 bcm/year, and from SRB to BG - 0.15 bcm/year. 2nd: the capacity will be increased from BG to SRB to 2,4 bcm/year, and from SRB to BG to 0,95 bcm/year, and later to 1,5 bcm/year, by construction of 2 CSs (20 MW each) and 2 new gas pipeline sections (from G Bogrov CS to N Iskar – 19 km and from V. Orašje to Nis – 161 km). 3rd: by construction of the looping VS Batulsi - G Bogrov CS (62 km) the capacity from BG to SRB will be increased to 3,2 bcm/year. In the direction from SRB to BG the construction of the pipeline Batajnica - V Orašje (116 km) will ensure transmission of 2 bcm/ year, and the construction of CS Batočina (20 MW) will increase the capacity from 2.0 bcm/year to up to 2.5 bcm/y.

Description

Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point

Operator

Year 2018

From Gas System To Gas System Capacity

51.0 GWh/d

IBS Future Operator

BGn

RS

Comment: Opeartor to be defined

Interconnector BG RS

51.0 GWh/d

IBS Future Operator

2018

RS

BGn

Comment: Operator to be defined

Sponsors Bulgarian section Ministry of Energy of Bulgaria

General Information

Promoter Operator

Ministry of Energy IBS Future Operator

100%

Host Country

Bulgaria Planned

Serbian section Serbijagas

Status

100%

Website

Project's URL

Publication Approval Status

Approved

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM