ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 27 of 620

Construction of new gas storage facility on the territory of Bulgaria

UGS-N-141 Update Date

Project

Storage Facility

Non-FID

Non-Advanced

04/05/2016

The construction of a new (second) gas storage is envisaged on the territory of Bulgaria. It could be constructed in suitable geological structure –depleted gas fields (onshore or offshore), salt caverns or aquifer. It must however be kept in mind that the construction of a new underground gas storage from the start of the geological and research activities to its commissioning could take not less than 7-8 years.

Description

Regulatory Decisions and similar material conditions

Sponsors Bulgartransgaz EAD

General Information

100%

Promoter Operator

Bulgartransgaz EAD Bulgartransgaz EAD

Host Country

Bulgaria Planned

Status

Website Publication Approval Status

Approved

NDP and PCI Information

Schedule

Start Date

End Date

Third-Party Access Regime

Pre-Feasibility Feasibility FEED Market Test Permitting Supply Contracts FID Construction Commissioning

Considered TPA Regime Considered Tariff Regime Applied for Exemption

Yes (2016-2025 Ten-year network development plan of BTG)

Regulated

Part of NDP

Not Applicable Not Relevant Not Relevant

NDP Number

section 5.3.2.

Exemption Granted

Currently PCI

No

Exemption in entry direction Exemption in exit direction

0.00% 0.00%

CBCA Decision Market Survey

No

Not Relevant (no CBCA decision)

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Southern Corridor GRIP 2017–2026 Annex B |

43