ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 44 of 620

Construction of a Looping CS Provadia – Rupcha village

TRA-N-594 Update Date

Project

Pipeline including CS

Non-FID

Non-Advanced

27/05/2016

Modernisation of the existing network for transit transmission with the construction of 50 km looping with prevailing diameter Dn 1200 from Provadia to the village of Rupcha, replacement of 20 km (2х10 km) 12 of existing gas pipelines with diameter of Dn 1000 from CS Strandja to the border with Turkey and increase in the capacity of CS Strandja with 10 MW. The realization of the project will ensure new capacity of 6 bcm/y (192,5 GWh/d) to Turkey.

Description

Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point

Operator

Year 2022

From Gas System To Gas System Capacity

192.5 GWh/d

Bulgartransgaz EAD

BGg/BGT

TRe

Strandzha (BG) / Malkoclar (TR)

Comment: a new looping

Sponsors Provadia - Rupcha Bulgartrasngaz EAD Strandja-IP BG/TR Bulgartrasngaz EAD

General Information

Promoter Operator

Bulgartransgaz EAD Bulgartransgaz EAD

100%

Host Country

Bulgaria Planned

Status

100%

Website

Project's URL

Publication Approval Status

Approved

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Southern Corridor GRIP 2017–2026 Annex B |

40

Made with FlippingBook - Online catalogs