ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 52 of 620

Pipelines and Compressor Stations - Alternative Variant

High capacity scenario, starting at Negru-Voda IP at RO-BG border, passing through BG using upgraded existing pipelines to Malkoclar IP at BG-TR border

Eastring - BG-1

Pipeline Section Eastring-BG-1

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Length of used existing pipeline - 259 km

1,200

0 0

0 0

Total

Pipelines and Compressor Stations - Alternative Variant

Low capacity scenario (low in direction N->S), starting at Negru-Voda IP at RO-BG border, passing through BG using upgraded existing pipelines to Malkoclar IP at BG-TR border

Eastring - BG-3

Pipeline Section Eastring-BG-3

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Length of used existing pipeline - 259 km

1,200

0 0

0 0

Total

Pipelines and Compressor Stations - Alternative Variant

Low capacity scenario (low in direction N->S), starting at new IP at RO-BG border, passing through BG using new pipeline to new IP at BG-TR border

Eastring - BG-4

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Data refers to the first stage - capacity 570 GWh/d, in case of increase of capacity up to 1140 GWh/d in 2025, compressor power at level of 374 MW will be needed

Eastring-BG-4

1,400

257

90

Total

257

90

PCI Details

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation prior to the commissioning of the project, Project concerns investment in reverse flow capacity

PCI Benefits

General Criteria Fulfilled Specific Criteria Fulfilled

Yes

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

Expected Gas Sourcing Caspian Region, Norway, Russia, LNG (), Iraq, Iran, Egypt, Israel, Turkmenistan, Kazakhstan, Cyprus, Azerbaijan, Any gas available at Turkish/European HUBs. For dire

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM