ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 4 of 620

GCA 2015/08: Entry/Exit Murfeld

TRA-N-361 Update Date

Project

Pipeline including CS

Non-FID Advanced

06/05/2016

The Project enables incremental capacity at the IP Murfeld in both directions (AT->SI, SI->AT). Moreover, physical RF capacity at the Entry Point Murfeld is achieved.

Description

Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point

Operator

Year 2019

From Gas System To Gas System Capacity

53.7 GWh/d

Gas Connect Austria GmbH

AT

SI

Comment: conversion from Nm³/h to kwh/h with a GCV of 11.19

Murfeld (AT) / Ceršak (SI)

166.5 GWh/d

Gas Connect Austria GmbH

2019

SI

AT

Comment: conversion from Nm³/h to kwh/h with a GCV of 11.19

Sponsors

General Information

GAS CONNECT AUSTRIA GmbH Gas Connect Austria GmbH

Promoter

Operator

Host Country

Austria Planned

Status

Website Publication Approval Status

Approved

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM