ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 386 of 620

Bordolano Second phase

UGS-F-1045 Update Date

Project

Storage Facility

FID

Advanced

13/06/2016

Description

The project is related to the conversion of the depleted reservoir of Bordolano, into a reservoir for the storage of methane gas

Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point

Operator

Year 2019

From Gas System To Gas System Capacity

185.0 GWh/d

STOGIT

STcIT

IT

Comment: Interconnection point Storage hub/Transportation grid is a commercial point. The capacity available is equal to the capacity offered or planned to be offered by the storage companies.

UGS - IT - Snam Rete Gas/STOGIT

109.0 GWh/d

STOGIT

2019

IT

STcIT

Comment: Interconnection point Storage hub/Transportation grid is a commercial point. The capacity available is equal to the capacity offered or planned to be offered by the storage companies.

Sponsors

General Information

Promoter Operator

STOGIT S.p.A.

STOGIT

Host Country

Italy

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM