Benefits

Main Driver Market Demand Main Driver Explanation RO>HU>AT transmission corridor (Black Sea or other gas source)

oBlack Sea gas or other gas source transmission to the European Gas Market The Hungarian projects taken as a whole main aim, is to enhance the flexibility of the Hungarian transmission system by connecting to neighbouring systems, ensuring reserves flow availability, and guaranteeing flow deliverability which will enhance the transmission systems security of supply position along with helping with further market integration. Barriers

Benefit Description

Barrier Type

Description

Market Market

Lack of market support Lack of market maturity

Regulatory

Low rate of return