ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 334 of 620

HU-UA reverse flow

TRA-N-586 Update Date Description

Project

Pipeline including CS

Non-FID

Non-Advanced

25/05/2016

The main aim of the project is to ensure firm capacity at IP Beregdaróc in the Hungary-Ukraine direction.

Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point Beregdaróc 800 (HU) - Beregovo (UA) (HU>UA)

Operator FGSZ Ltd.

Year 2020

From Gas System To Gas System Capacity

180.0 GWh/d

HU

UAe

Sponsors FGSZ Ltd.

General Information

100%

Promoter Operator

FGSZ Ltd. FGSZ Ltd. Hungary Planned

Host Country

Status

Website Publication Approval Status

Approved

NDP and PCI Information

Schedule

Start Date

End Date

Third-Party Access Regime

Part of NDP NDP Number

Pre-Feasibility Feasibility FEED Market Test Permitting Supply Contracts FID Construction Commissioning

Considered TPA Regime Considered Tariff Regime Applied for Exemption

Yes (Hungarian TYNDP 2015)

Regulated Regulated

12.17.

No No

Currently PCI

Exemption Granted

No

CBCA Decision Market Survey

Exemption in entry direction Exemption in exit direction

No

0.00% 0.00%

Not Relevant (no CBCA decision)

2020

2020

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM