ENTSOG GRIP SC 2017-2026 / Annex B - Project Information
Current TYNDP : TYNDP 2017 - Annex A
Page 332 of 620
NDP and PCI Information
Schedule
Start Date
End Date 12/2015 12/2017 03/2018 10/2016 03/2018 08/2018 03/2018 05/2020
Third-Party Access Regime
Part of NDP NDP Number
Pre-Feasibility
Considered TPA Regime Considered Tariff Regime Applied for Exemption
Yes (Hungarian TYNDP 2015)
Regulated Regulated
Feasibility
12.15.1. - 12.15.2.
01/2017 10/2016
FEED
No No
Currently PCI
Market Test Permitting
Exemption Granted
Yes (6.25.2.)
10/2016
CBCA Decision Market Survey
Exemption in entry direction Exemption in exit direction
Supply Contracts
No
0.00% 0.00%
Not Relevant (no CBCA decision)
FID
Construction
09/2018
Commissioning
2020
2020
Pipelines and Compressor Stations Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
+30 MW compressor station, in order to put natural gas from the Hungarian national system (gas storage, other sources) to Tesla pipeline.
Hungarian section
1,200
361
50
Total
361
50
PCI Details
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation prior to the commissioning of the project
PCI Benefits
General Criteria Fulfilled Specific Criteria Fulfilled
Yes
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Time Schedule
Grant Obtention Date Delay Since Last TYNDP
1 year
Delay Explanation
Russian/Turkey conflict.
Expected Gas Sourcing
Caspian Region, Russia
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM