ENTSOG GRIP SC 2017-2026 / Annex B - Project Information
Current TYNDP : TYNDP 2017 - Annex A
Page 316 of 620
Romanian-Hungarian reverse flow Hungarian section 1st stage
TRA-N-286 Update Date
Project
Pipeline including CS
Non-FID
Non-Advanced
22/06/2016
A new compressor station at Csanádpalota with 2 units (4.5 MW each) - necessary to create pressure conditions for the transportation capacity of 1.75 bcm/a from and towards Romania.
Description
Regulatory Decisions and similar material conditions
Capacity Increments Variant For Modelling Point
Operator FGSZ Ltd.
Year 2020
From Gas System To Gas System Capacity
Csanadpalota
48.9 GWh/d
RO
HU
Sponsors FGSZ Ltd.
General Information
100%
Promoter Operator
FGSZ Ltd. FGSZ Ltd. Hungary Planned
Host Country
Status
Website Publication Approval Status
Approved
Enabled Projects
Project Code Project Name TRA-N-377 Romanian-Hungarian reverse flow Hungarian section 2nd stage
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM