ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 241 of 620

NDP and PCI Information

Schedule

Start Date

End Date

Third-Party Access Regime

Pre-Feasibility Feasibility FEED Market Test Permitting Supply Contracts FID Construction Commissioning

Considered TPA Regime Considered Tariff Regime Applied for Exemption

No (The Project Promoter is not a Transmission System Operator and as such does not have the obligation to submit a National Development Plan.)

Regulated Regulated

Part of NDP

No

Exemption Granted

Not Relevant

NDP Number

Exemption in entry direction Exemption in exit direction

0.00% 0.00%

Currently PCI

No

CBCA Decision Market Survey

No

2022

2022

Not Relevant (no CBCA decision)

Technical Information (UGS)

Storage Facility

South Kavala

Storage Facility Type

Aquifer

Multiple-Cycle

Yes

Working Volume (mcm)

360.00

PCI Details

Project aims at fulfilling the infrastructure standard (N-1) rule at regional level in accordance with Article 6(3) of Regulation EU, Project aims at supplying directly or indirectly at least two Member States

PCI Benefits

General Criteria Fulfilled Specific Criteria Fulfilled

Yes

Competition, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

Time Schedule

Grant Obtention Date Delay Since Last TYNDP

2 years

Delay Explanation

Decision on the procedure to select the project promoter and time needed to prepare the relevant tender procedure.

Expected Gas Sourcing Caspian Region, Russia, LNG . The project may source gas from all gas sources supplying or transitting Greece

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Southern Corridor GRIP 2017–2026 Annex B |

144