NDP and PCI Information
Schedule
Start Date
End Date
Third-Party Access Regime
Pre-Feasibility Feasibility FEED Market Test Permitting Supply Contracts FID Construction Commissioning
Considered TPA Regime Considered Tariff Regime Applied for Exemption
No (The Project Promoter is not a Transmission System Operator and as such does not have the obligation to submit a National Development Plan.)
Regulated Regulated
Part of NDP
No
Exemption Granted
Not Relevant
NDP Number
Exemption in entry direction Exemption in exit direction
0.00% 0.00%
Currently PCI
No
CBCA Decision Market Survey
No
2022
2022
Not Relevant (no CBCA decision)
Technical Information (UGS)
Storage Facility
South Kavala
Storage Facility Type
Aquifer
Multiple-Cycle
Yes
Working Volume (mcm)
360.00
PCI Details
Project aims at fulfilling the infrastructure standard (N-1) rule at regional level in accordance with Article 6(3) of Regulation EU, Project aims at supplying directly or indirectly at least two Member States
PCI Benefits
General Criteria Fulfilled Specific Criteria Fulfilled
Yes
Competition, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Time Schedule
Grant Obtention Date Delay Since Last TYNDP
2 years
Delay Explanation
Decision on the procedure to select the project promoter and time needed to prepare the relevant tender procedure.
Expected Gas Sourcing Caspian Region, Russia, LNG . The project may source gas from all gas sources supplying or transitting Greece