ENTSOG GRIP SC 2017-2026 / Annex B - Project Information
Current TYNDP : TYNDP 2017 - Annex A
Page 224 of 620
NDP and PCI Information
Schedule
Start Date
End Date 12/2010 06/2014 12/2016 03/2017 01/2015
Third-Party Access Regime
Pre-Feasibility
Considered TPA Regime Considered Tariff Regime Applied for Exemption
No (The Project is not included in the NDP because it is an Independent Natural Gas System and therefore the NTSO is not obliged to include it in the NDP because it is not the Project's promoter and/or operator. )
Regulated Regulated
Feasibility
01/2014 05/2016
FEED
No
Part of NDP
Market Test Permitting
Exemption Granted
Not Relevant
12/2010
Exemption in entry direction Exemption in exit direction
Supply Contracts FID
0.00% 0.00%
NDP Number
12/2016 06/2018
Construction
04/2017
Currently PCI
Yes (6.9.1)
Commissioning
2018
2018
CBCA Decision Market Survey
No
Not Relevant (no CBCA decision)
Technical Information (LNG)
LNG terminal in northern Greece / Alexandroupolis
LNG Facility
Expected Volume (bcm/y) Storage Capacity (m3)
6
New regaseification technical capacity increment will be available from start of operations.
170,000 170,000
4 storage tanks
Ship Size (m3)
DWT 85,000 MT, LOA 300-310 m., Breadth 46 m., Draft 12m.
Reloading Ability
Yes
PCI Details
Project aims at fulfilling the infrastructure standard (N-1) rule at regional level in accordance with Article 6(3) of Regulation EU, Project aims at supplying directly or indirectly at least two Member States
PCI Benefits
General Criteria Fulfilled Specific Criteria Fulfilled
Yes
Competition, Market Integration, Security of Supply, Sustainability
Market Integration - Regional (SEE + Serbia + FYROM) and beyond (e.g. Hungary and through across the NSI gas corridor) Security of Supply through inter alia source and route diversification- Greece, Bulgaria, Serbia, FYROM, Hungary, Ukraine, Turkey Enhances competition in the region by introducing new sources and routes of supply Sustainability - Supports back up to renewables and power to gas
Specific Criteria Fulfilled Comments
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM