ENTSOG GRIP SC 2017-2026 / Annex B - Project Information
Current TYNDP : TYNDP 2017 - Annex A
Page 220 of 620
Melendugno - IT / TAP
Comment: GCV used for capacity calculations: 11.071 kWh/Sm3.
142.0 GWh/d
Trans-Adriatic Pipeline AG
2019
GR
GR/TAP
Comment: GCV used for capacity calculations: 11.071 kWh/Sm3.
Incremental capacity available for allocation is subject to a check of the system's capabilities and dependent on the capacity bookings in place. Trans-Adriatic Pipeline AG 2019 GR/TAP GR
Nea Mesimvria
142.0 GWh/d
Comment: GCV used for capacity calculations: 11.071 kWh/Sm3.
Incremental capacity available for allocation is subject to a check of the system's capabilities and dependent on the capacity bookings in place.
Sponsors BP
General Information
20%
Promoter Operator
Trans Adriatic Pipeline AG Trans-Adriatic Pipeline AG
Snam
20%
Host Country
Greece
SOCAR
20%
Status
Planned
Fluxys
19%
Website
Project's URL
Publication Approval Status
Approved
Enagas
16%
Axpo
5%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Southern Corridor GRIP 2017–2026 Annex B |
124