NDP and PCI Information
Schedule
Start Date
End Date
Third-Party Access Regime
Pre-Feasibility Feasibility FEED Market Test Permitting Supply Contracts FID Construction Commissioning
Considered TPA Regime Considered Tariff Regime Applied for Exemption
No (This project is not included in the National Development Plan because no application has been made, by the promoter of the East-Med pipeline, for the connection of this project to the Greek gas transmission system.)
Regulated Regulated
Part of NDP
Not Relevant Not Relevant
Exemption Granted
NDP Number
Exemption in entry direction Exemption in exit direction
0.00% 0.00%
Currently PCI
No
2022
2022
CBCA Decision Market Survey
No
Not Relevant (no CBCA decision)
PCI Details
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation prior to the commissioning of the project
PCI Benefits
General Criteria Fulfilled Specific Criteria Fulfilled
Yes
Competition, Market Integration, Security of Supply
Specific Criteria Fulfilled Comments
Expected Gas Sourcing
Cyprus, Israel
Benefits
Main Driver
Market Demand
Main Driver Explanation Benefit Description