ENTSOG GRIP SC 2017-2026 / Annex B - Project Information
Current TYNDP : TYNDP 2017 - Annex A
Page 255 of 620
Compressor station at Nea Messimvria
TRA-N-971 Update Date
Project
Pipeline including CS
Non-FID
Non-Advanced
04/07/2016
The project consists of the implementation of a 27 MW compressor station in order to enable flow from the Greek transmission system to TAP. This project is the second phase of development of project "TRA-N-941-Metering and Regulating station at Nea Messimvria" .
Description
Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point
Operator DESFA S.A.
Year 2022
From Gas System To Gas System Capacity
Nea Mesimvria
142.0 GWh/d
GR
GR/TAP
Sponsors
General Information
Promoter Operator
DESFA S.A. DESFA S.A.
Host Country
Greece
Status
Planned
Website Publication Approval Status
Approved
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM