ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 9 of 620

NDP and PCI Information

Schedule

Start Date

End Date

Third-Party Access Regime

Pre-Feasibility Feasibility FEED Market Test

Considered TPA Regime Considered Tariff Regime Applied for Exemption

No (The BBI project is a new project and will be part of the NDP 2017-2026.)

Regulated Regulated

Part of NDP

NDP Number

GCA2015/01

No

Exemption Granted

04/2016

Not Relevant

Currently PCI

No

Permitting

03/2016

Exemption in entry direction Exemption in exit direction

Supply Contracts FID Construction Commissioning

0.00% 0.00%

CBCA Decision Market Survey

No

Not Relevant (no CBCA decision)

10/2020

2020

2020

Pipelines and Compressor Stations Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

The incremental capacity represents an entry capacity extension between the market areas of CZ and AT

Břeclav-Baumgarten Interconnection (BBI) AT

1,400

49

10

Total

49

10

Benefits

Main Driver

Market Demand

Main Driver Explanation Benefit Description

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Southern Corridor GRIP 2017–2026 Annex B | 11