ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 282 of 620

Permit granting process for the project has started in 10/2013 by requesting the EIA which was approved in 04/2014. Location permit was approved in 09/2015. Accordingly to the specific phase of the projects permits will be modified/ obtained. Project named LNG terminal on the Island of Krk was declared on Government of Republic of Croatia session from 16th of July 2015 a project of strategic importance for the Republic of Croatia. The Act on strategic investments enables this kind of projects to have the highest priority with faster and simplified procedure in obtaining necessary documents and permits for the project implementation. Potential barrier of enough pipeline capacity availability. The pipelines need to be build but FID has not yet been reached, which is a precondition for LNG terminal realization in forseen deadlines. Market Background Analysis was carried out and it indicated that the market has commercial potential. Open Season procedure will serve as an official confirmation of that analysis. The binding phase of Open Season has been carried out. Signing of the contract is expected to be upon NRA's approval of missing regulatory framework for liquefied natural gas i.e. methodology for determination of tariff for receiving LNG and gas send-out. Intergovernmental Agreements

Permit Granting

Political

Others

Market

Agreement CESEC MoU

Agreement Description

Is Signed Agreement Signature Date

Memorandum of Understanding

Yes

10/07/2015

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Southern Corridor GRIP 2017–2026 Annex B | 91

Made with FlippingBook - Online catalogs