ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 280 of 620

Sponsors HEP d.d.

General Information

50%

LNG Hrvatska d.o.o. za poslovanje ukapljenim prirodnim plinom LNG Hrvatska d.o.o.

Promoter

Plinacro d.o.o.

50%

Operator

Host Country

Croatia Planned

Status

Website

Project's URL

Publication Approval Status

Approved

NDP and PCI Information

Schedule

Start Date

End Date 01/2013 01/2014 12/2015 10/2015

Third-Party Access Regime

Pre-Feasibility

Considered TPA Regime Considered Tariff Regime Applied for Exemption

Yes (Desetogodišnji plan razvoja plinskog...)

Not Applicable Not Applicable

Part of NDP

Feasibility

07/2012 06/2015

NDP Number

6.5.1.

FEED

No No

Market Test

Exemption Granted

Currently PCI

Yes (6.5.1.)

Permitting Supply Contracts FID Construction Commissioning

Exemption in entry direction Exemption in exit direction

0.00% 0.00%

CBCA Decision Market Survey

No

Not Relevant (no CBCA decision)

2018

2018

Technical Information (LNG)

The import terminal for the liquefied natural gas (LNG) on the Island of Krk

LNG Facility

1st stage - 1-4 bcm/y (According to FSRU ship and pepeline availability), 2nd stage - 3,5 bcm/y, 3rd stage - 5bcm/y, 4th stage - 8.75 bcm/y 1st stage depending on FSRU storage capacity availability, 2nd stage 1 x 150,000.00, 3rd stage 2 x 150,000.00, 4th stage 2 x 150,000.00 75,000.00 – 265,000.00 (Jetty construction and sea depth will enable Q Max LNG carriers to bearth at the site. The size of the carriers that are going to berth alongside to the FSRU will depend on the storage and regasification capabilities of the FSRU)

Expected Volume (bcm/y)

4

Storage Capacity (m3)

300,000

Ship Size (m3)

265,000

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM