ENTSOG GRIP SC 2017-2026 / Annex B - Project Information
Current TYNDP : TYNDP 2017 - Annex A
Page 292 of 620
Interconnection Croatia-Bosnia and Herzegovina (west)
TRA-N-303 Update Date
Project
Pipeline including CS
Non-FID
Non-Advanced
13/07/2016
Interconnection Croatia-Bosnia and Herzegovina on route Licka Jesenica-Rakovica in Croatia to border with Bosnia and Herzegovina. Bosnian part is from Trzac to Bosanska Krupa with branches to Bihać and Velika Kladusa.
Description
Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point
Operator
Year 2026 2026
From Gas System To Gas System Capacity
81.0 GWh/d 81.0 GWh/d
Plinacro Ltd Plinacro Ltd
BA HR
HR BA
Rakovica (HR) / Trzac (BA)
Sponsors Croatian part Plinacro d.o.o. part in B&H BH Gas
General Information
Promoter Operator
Plinacro Ltd Plinacro Ltd
100%
Host Country
Croatia Planned
Status
100%
Website
Project's URL
Publication Approval Status
Approved
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Southern Corridor GRIP 2017–2026 Annex B |
82