ENTSOG GRIP SC 2017-2026 / Annex B - Project Information
Current TYNDP : TYNDP 2017 - Annex A
Page 303 of 620
NDP and PCI Information
Schedule
Start Date
End Date
Third-Party Access Regime
Part of NDP NDP Number
Pre-Feasibility Feasibility FEED Market Test
Considered TPA Regime Considered Tariff Regime Applied for Exemption
Yes (2017-2026)
Regulated Regulated
1.21
12/2015
10/2016
No No
Currently PCI
Exemption Granted
08/2016 01/2023
Yes (6.5.2)
Permitting
09/2014
CBCA Decision Market Survey
Exemption in entry direction Exemption in exit direction
Supply Contracts FID
No
70.00% 30.00%
Not Relevant (no CBCA decision)
01/2020 01/2023
Construction
01/2021
Commissioning
2023
2023
Pipelines and Compressor Stations Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Kozarac-Slobodnica
800
128 128
Total
PCI Details
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation prior to the commissioning of the project, Project concerns investment in reverse flow capacity
PCI Benefits
General Criteria Fulfilled Specific Criteria Fulfilled
Yes
Competition, Market Integration, Security of Supply, Sustainability
Project will connect several, in the future exceptionally important, points of the Croatian gas transmission system. It is the future strategic gas transmission connector of great significance and is an integral part of the North – South European Corridor named as the North-South (Baltic – Adriatic) Gas Connection. Its purpose is linking the Polish and the Croatian LNG (Liquefied Natural Gas) solutions. This gas pipeline (as well as all the pipelines to which it connects and the associated gas nodes) will provide gas transmission in all directions, i.e. it will satisfy all transmission requirements and will maximise the value of the IAP and LNG projects in Croatia and the region. In addition, it will increase the use of the existing system and the new interconnection with Hungary.
Specific Criteria Fulfilled Comments
Time Schedule
Grant Obtention Date Delay Since Last TYNDP Delay Explanation
24/11/2015
Project depend on LNG project
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Southern Corridor GRIP 2017–2026 Annex B |
80