ENTSOG GRIP SC 2017-2026 / Annex B - Project Information

Current TYNDP : TYNDP 2017 - Annex A

Page 273 of 620

NDP and PCI Information

Schedule

Start Date

End Date

Third-Party Access Regime

Part of NDP NDP Number

Pre-Feasibility Feasibility FEED Market Test

Considered TPA Regime Considered Tariff Regime Applied for Exemption

Yes (2017-2026)

Regulated Regulated

1.11, 1.12

No No

Currently PCI

Exemption Granted

No

08/2016 10/2023

Permitting

01/2010

CBCA Decision Market Survey

Exemption in entry direction Exemption in exit direction

Supply Contracts FID

No

70.00% 30.00%

Not Relevant (no CBCA decision)

10/2021 10/2023

Construction

01/2022

Commissioning

2023

2023

Pipelines and Compressor Stations Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Slobodnica - Sotin

16 mcm daily-total capacity

800 800

97

Sotin- Bačko Novo Selo

I section

5

Total

102

PCI Details

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation prior to the commissioning of the project, Project concerns investment in reverse flow capacity

PCI Benefits

General Criteria Fulfilled Specific Criteria Fulfilled

Yes

Competition, Market Integration, Security of Supply, Sustainability

This project is an interconnection of the gas systems of Croatia and Serbia on the route Slobodnica-Sotin-Bačko Novo Selo and it is primarily intended for transport of LNG from the terminal on the island of Krk as well as from other possible routes and directions towards SEE countries. The most important impacts and benefits of the project: 1) It provides viable and secure supply of SEE countries, which are heavily dependent on the Russian gas and jeopardized by the Russian giving up on the South Stream project and the announcement regarding termination of gas transmission via Ukraine after 2019 2) It provides diversification of supply (also in case the previously mentioned threats fail to occur) and thereby competitiveness and lower prices for users 3) It facilitates market integration

Specific Criteria Fulfilled Comments

Expected Gas Sourcing

Caspian Region, LNG (HR), it will be gas from Croatian transport system, Croatian UGS

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM