Interconnection Croatia/Serbia (Slobdnica-Sotin-Bačko Novo Selo)
TRA-N-070 Update Date
Project
Pipeline including CS
Non-FID
Non-Advanced
13/07/2016
Covering Croatia and Serbia, connecting the Croatian gas transmission system to the Serbian gas transmission system Slobodnica - Sotin (Croatia) - Bačko Novo Selo (Serbia). It will be new interconnection, new entry point and transmission route for the needs of Serbia; it will be SoS and diversification of supply route for Serbia. It will enable Serbia access to Croatian UGS and enable supply of gas from Austria, Slovenia and Italy by the Croatian gas transmission system.
Description
Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point
Operator
Year 2023 2023
From Gas System To Gas System Capacity
227.5 GWh/d 227.5 GWh/d
Plinacro Ltd Plinacro Ltd
HR RS
RS HR
Slobodnica - Sotin (HR) / Bačko Novo Selo (RS)
Sponsors Croatian section Plinacro Serbian section Srbijagas
General Information
Promoter Operator
Plinacro Ltd Plinacro Ltd
100%
Host Country
Croatia Planned
Status
100%
Website
Project's URL
Publication Approval Status
Approved