Interconnection Croatia-Bosnia and Herzegovina (South)
TRA-N-302 Update Date
Project
Pipeline including CS
Non-FID Advanced
13/07/2016
South Interconnection of Croatia and B&H - the pipeline is a new supply route for Bosnia and Herzegovina that will enable the reliable and dievrsifed natural gas supply. The pipeline will enable the flow of IAP to Bosnia and Herzegovina
Description
Regulatory Decisions and similar material conditions
Capacity Increments Variant For Modelling Point
Operator
Year 2021 2021
From Gas System To Gas System Capacity
81.0 GWh/d 81.0 GWh/d
Plinacro Ltd Plinacro Ltd
BA
HR/IAP
Posušje
HR/IAP
BA
Sponsors Croatian part of both options Plinacro d.o.o.
General Information
Promoter Operator
Plinacro Ltd Plinacro Ltd
100%
Host Country
Croatia Planned
parts in B&H BH Gas
Status
100%
Website
Project's URL
Publication Approval Status
Approved
Enabled Projects
Project Code Project Name TRA-N-068 Ionian Adriatic Pipeline
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM