Delay Since Last TYNDP Delay Explanation

The preparatory work will be performed in phases, depending on the development of the LNG project,

Expected Gas Sourcing Caspian Region, LNG (HR,QA), it will be gas from Croatia transport system, Croatian UGS and all import routes (LNG and IAP) Comments about the Third-Party Access Regime TPA regime is not defined yet, Exemption Regime possibly Benefits Main Driver Market Demand

This gas pipeline passes only through the territory of the Republic of Croatia. However, it has regional significance since it is the main evacuation gas pipeline from the LNG solution on the island of Krk towards Hungary and it is its main role. This gas pipeline increases utilisation of the interconnection with Hungary so it has influence on Hungary but also further on Slovakia and Ukraine. The gas pipeline shall be also significant for third countries; Serbia, Bosnia and Herzegovina by constructing interconnection with these countries. The project is the main gas pipeline for transport of LNG from the terminal on the island of Krk as well as from other possible sources, such as gas from the Ionian-Adriatic Pipeline , towards CEE and SEE countries. At the same time, in addition to already constructed interconnection gas pipeline with Hungary, Slobodnica-Donji Miholjac-Dravaszerdahely, it presents the Croatian part of the strategic transregional gas pipeline connection Adriatic-Baltic the aim of which is to connect the Polish and Croatian LNG terminal. The most important impacts and benefits of this project: 1. It provides viable and secure supply of CEE and SEE countries, which are heavily dependent on the Russian gas and jeopardized by the Russian giving up on the South Stream project and the announcement regarding termination of gas transmission via Ukraine after 2019. 2. It provides diversification of supply (also in case the previously mentioned threats fail to occur) and thereby competitiveness and lower pr

Main Driver Explanation

Benefit Description

Barriers

Barrier Type

Description

Others

Directly connected and depening on the LNG project on the island of Krk

Financing

Availability of funds and associated conditions