Benefits

Main Driver

Market Demand

This project is of great interest for the development of the natural gas sector in B&H, as its implementation would provide new route of supply B&H with gas, with a possibility of diversification of supply sources and increase in security of supply of the existing transportation system of B&H, and especially in the circumstances of the natural gas supply of the refineries Brod and Modrica and planned power plant (PP) Zenica and CCGT Kakanj, as well as the expansion of the market and increase in the competitiveness of natural gas. The construction of this gas pipeline would enable the B&H gas transmission system to connect with the Croatian gas transmission system through the pipeline from Slavonski Brod to Donji Miholjac, and then with the Hungarian pipeline. It will connect BH market to the new LNG in Croatia and Baumgarten via Slovenia. It will be new interconnection, new entry point and transmission route for the needs of BH; it will be SoS and diversification of supply route for Bosnia and Herzegovina. It will anable BH access to Croatian UGS.This project is an interconnection of the gas systems of Croatia and Bosnia and Herzegovina on the route Slobodnica-Brod-Zenica. The most important impacts and benefits of this project: 1. It provides viability and security of supply of Bosnia and Herzegovina; 2. It provides diversification of supply routes and sources for the market of Bosnia and Herzegovina; 3. It provides development of the gas market in Bosnia and Herzegovina; 4. Introducing an environmentally more acceptable energy source (replacement for firewood, coal, fuel oil and complementary generation to renewable energy, and the potential for new CCGT and PP); 5. Reducing CO2 and SO2 emissions in the B&H and region and facilitating economic development. Barriers This project is politicaly very sensitive and depends on the agreement with Republika Srpska and agremments within B&H and its TSOs (BH Gas and GasRES) Intergovernmental Agreements Description

Main Driver Explanation

Benefit Description

Barrier Type

Political

Agreement

Agreement Description

Is Signed Agreement Signature Date

Letter of Intent

between Plinacro and BH Gas for all projects of interconnection

Yes Yes

06/04/2011 26/06/2006

Memorandum of understanding

signed between Plinacro and BH Gas

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM