ENTSOG GRIP BEMIP 2014-2023 / Annex: Infrastructure Projects
The North-South corridor in Western Poland - GAZ-SYSTEM
280
TRA-N-247
The North-South corridor in Western Poland
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter
GAZ-SYSTEM S.A.
Operator
GAZ-SYSTEM S.A.
TEN-E Project ?
Project of Common Interest
Interested by PCI ?
Yes
IGAs
None
en.gaz-system.pl/nasze-inwestycje/krajowy-system- przesylowy/
Web Link
Undefined (100,00%)
Gas Transmission OperatorGAZ- SYSTEM S.A. (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime
End of permitting phase
# of Pipelines, nodes, CS
Regulated
10
Considered Tariff Regime
FID
Total Pipeline Length (km)
Regulated
2015
+739.00
Total Compressor Power (MW)
Applied for Exemption ?
No
Construction
+7.00
Exemption granted ?
Commissioning
Expected Load Factor
Not relevant
2018
% Exemption in entry direction
Last completed Phase :
0%
Planned
% Exemption in exit direction
0%
Baltic Energy Market Interconnection Plan GRIP 2014–2023 Annex | 38