ENTSOG GRIP BEMIP 2014-2023 / Annex: Infrastructure Projects
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction
Klaipeda (LNG)
Yes
entry
62.00
LNG Terminals Lithuania
Hub Lithuania
DESCRIPTION OF THE PROJECT
None EXPECTED BENEFITS
Security of supply, diversification of sources, diversification of routes, N-1 national (Lithuania), N-1 regional (Baltic states); this project would provide capacity to transport gas from LNG terminal in Klaipeda to other Baltic states for the needs of national consumption as well as to the Inčukalns underground gas storage (Latvia) as well as would provide an opportunity for the market players of certain Baltic states to diversify gas supply routes and sources and possibly enhance competition in the gas market.
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
Expected the EU financial support (preliminary)
AB Amber Grid
Baltic Energy Market Interconnection Plan GRIP 2014–2023 Annex | 29