ENTSOG GRIP BEMIP 2014-2023 / Annex: Infrastructure Projects
Tie-in of Norwegian off-shore natural gas transmission system
282
Tie-in of Norwegian off-shore natural gas transmission system to Danish off-shore natural gas infrastructure
TRA-N-218
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter
Maersk Oil and Gas AS
Operator
Maersk Oil and Gas A/S
TEN-E Project ?
Not part of TEN-E
Interested by PCI ?
Not defined yet
IGAs
None
TBD (50%)
TBD (50%)
Web Link
Undefined (100,00%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
# of Pipelines, nodes, CS
Considered TPA Regime
End of permitting phase
1
Negotiated (e.g. Exemption)
Considered Tariff Regime
FID
Total Pipeline Length (km)
Regulated
+175.00
Total Compressor Power (MW)
Applied for Exemption ?
Construction
No
2013
Exemption granted ?
Commissioning
Expected Load Factor
Not relevant
2014/4
+0.80
% Exemption in entry direction
Last completed Phase :
0%
FEED
% Exemption in exit direction
0%