ENTSOG GRIP BEMIP 2014-2023 / Annex: Infrastructure Projects
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction
UGS - PL - Gaz-System/Magazynowania
118.80
Storage Poland
Hub Poland
Yes
exit
DESCRIPTION OF THE PROJECT
Under gas storage (KPMG) extension in order to increase working gas capacity
EXPECTED BENEFITS
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing