PROJECTED CAPACITY INCREASES

Interconnection

Capacity (GWh/d)

From Zone

To Zone

Modelled Direction

UGS - PL - Gaz-System/Magazynowania

Yes

entry

10.34

Hub Poland

Storage Poland

DESCRIPTION OF THE PROJECT

Underground gas storage (PMG) extension in order to increase working gas capacity injection and withdrawal rates. Instalation of additional compressor station to allow for a more flexible opeartion.

EXPECTED BENEFITS

COMMENTS ABOUT THE PROJECT FINANCING

Public financing

Private financing

Multilateral financing