Overview of the Rule

All TSOs must publish all the information on ENTSOG’s Transparency Platform in the standardised table as set out in Article 31(3): in English; per IP; the direction of gas flow; the names of the relevant TSOs; the start and end time of the product; whether the capacity is firm or interruptible; the indication of the standard capacity product; and the applicable tariff per kWh/h and per kWh/d in the local currency and in euro.

Responses

All TSOs (46 TSOs) Has all information to be published on ENTSOG's Transparency Platform in the standardised table been published in the manner as set out in Art. 31(3)?

3

2

Yes, 41 (from 21 MSs) NRA responsibility, 2 (from 1 MS) No, 3 (from 3 MS)

41

Figure 14: Manner of publication on ENTSOGs Transparency Platform in the standardised table

Æ 41 TSOs have published the required information on ENTSOG’s Transparency Platform in the standardised table as set out in Article 31(3). However, one has not completely published all the required information as what they will publish will be determined by a decision on a derogation application, and another TSO has not published a simulation of all the costs for flowing 1 GWh/d/year as technically they only have virtual counter-flow capacity products available. Æ For two TSOs a decision on who is to publish has not been made and is recorded here as ‘NRA responsibility’. Æ Three TSOs answered ‘no’ as they have not published anything on ENTSOG’s Transparency Platform in the standardised table, due to it being non-applicable for one TSO, as they do not have an IP, and two TSOs will add/update all their information on the Transparency Platform in 2018.