DELIVERABLE &  COMPLETION DATE

ACTIVITY

GOAL

STATUS / COMMENTS

CONSULTATION WITH

SYSTEM OPERATION AREA: PROJECT PLAN FOR TRANSPARENCY WORKING GROUP

Additional tools for Transparency Platform

Increased usability and user friendliness

Several new TP functionalities were implemented during 2016 with aim of enhancing data usability and publication com- prehensiveness

Gas TSOs, TP users and other stakeholders

Completed as planned

10th public workshop on Transparency

Ensure transparent dialog with stakeholders

8 December 2016

Gas TSOs, TP users, ACER, EC and other stakeholders

Completed

Improvement of TP data quality

On-going activity, in progress

Enhance data publication comprehensiveness and usability

Ongoing process of data publication monitoring

Improvement of TP data frequency uploads

Gas TSOs, EFET

80% complete The remaining TSOs will follow

Publish physical flows in hourly granularity and frequency for cross- border points from 1 May 2016

39 TSOs have started to publish more frequently than required by the regulation during 2016 7 April 2016 ensuring compliance ongoing activity

Follow-up to REMIT

Ensure timely implementation and compliance of TSOs with REMIT re- quirements

Completed On-going activity, in progress

Follow-up to NC transparency obligation

Ensure timely implementation of new transparency requirements.

Ongoing effort

Gas TSOs, ENTSOG Working Groups, TP users and other stakeholders

Ongoing activity, in progress

TP collaboration tool for information provision

Utilise the TP framework in emergency situations

Ongoing effort

RCSG KG

On-going activity embedded in the RCSG KG under Interoperability