ENTSOG Annual Report 2015
DELIVERABLE & COMPLETION DATE
GOAL
STATUS / COMMENTS
CONSULTATION WITH
SYSTEM OPERATION AREA: PROJECT PLAN FOR TRANSPARENCY WORKING GROUP
Gas TSOs, TP users and other stakeholders
Completed
Implementation of new TP functionalities
Several new TP functionalities were implemented during 2015 with aim of enhancing data usability and publication comprehensiveness.
Collaboration with TSOs to improve TP data quality and completeness Joint ENTSOG – TSO effort to improve data quality and completeness.
Ongoing process of data publication monitoring.
Gas TSOs, TP users and other stakeholders
In progress
Gas TSOs, TP users and other stakeholders
In progress
TP users support
Ongoing process of interaction with stakeholders regarding TP operation and information
ENTSOG REMIT implementation
7 October 2015
Gas TSOs, ACER
Completed
Support TSOs with REMIT implementation
Ongoing effort
Gas TSOs, ACER
In progress
Follow-up and implementation of transparency requirements arising from NC CAM,
Ongoing effort
Gas TSOs, ENTSOG Working Groups, TP users and other stakeholders
In progress
NC INT and NC TAR and liaison with relevant ENTSOG WGs
Hold public workshop on transparency on annual basis
4 February 2016
Gas TSOs, TP users, ACER, EC and other stakeholders
Completed
DELIVERABLE & COMPLETION DATE
GOAL
STATUS / COMMENTS
CONSULTATION WITH
SYSTEM OPERATION AREA: PROJECT PLAN FOR INTEROPERABILITY WORKING GROUP
Develop an interconnection agreement template, send it for opinion to ACER and publish it on ENTSOG’s website
ENTSOG to publish an IA template draft on its website by 30 June 2015. After NRA and ACER review to publish final version by the 31 December ENTSOG to develop questionnaire by 1 November and TSOs to answer by 31 December 2015. ENTSOG to write report by 30 April 2016
ACER/EC and NRAs
Completed
Develop and publish an INT NC & DE pre-implementation status report
ENTSOG, TSOs
ENTSOG to produce questionnaire and TSOs to answer. ENTSOG to issue report with AR 2015
Develop the basic ideas for the Long-Term Gas Quality Outlook
Carry out pilot test on TYNDP 2015 data; assess possible methodologies
TYNDP stakeholders in 2015
To be further developed in 2016
CEN GQ Standard issued in 2015 and Pilot II reactivated in 2015. EC invited ENTSOG to amend INT NC
CEN TC 234/WG 11, CEN PC 408, Marcogaz, EEASE-Gas, Member State TSOs
Follow-up the processes related to gas quality standardisation
Monitor CEN activities during 2015 meetings; Report to Gas Quality KG and Interoperability WG
Develop further the Early Warning System mechanism
Implement an Early Warning Team North-West by the 30 June 2015. Contact EC to discuss how EWS could be used as part of the revision of SoS Regulation Prepare and carry out workshops to present and clarify INT NC rules to 3 rd Country TSOs in close cooperation with EnC
Member TSOs, 3 rd Country TSOs, Energy Community, EC
Completed, In progress
Forward recommendations to 3 rd Country TSOs related to INT NC
Member TSOs, 3 rd Country TSOs, EnC
Workshop held in Vienna on 18 June 2015
CNOT on CAM/CMP
BRS and IG for data exchange related to implementation of CAM and CMP
Member TSOs and EASEE-gas (Edig@s workgroup)
In progress
Workshop held in October 2015
Follow-up on implementation of AS4 and organise workshop to discuss implementation issues and gain experience Codes through weekly updates to Central Issuing Office and ENTSOG website; deliver final responses to requests within 10 days at most
AS4 implementation support
Operate the Local Issuing Office for Energy Identification Coding Schema