ENTSOG Annual Report 2014
Work Programme Status
These tables provide an overview of the activities in ENTSOG’s three main business areas. The commented tasks originate from the Annual Work Programme 2014.
DELIVERABLE & COMPLETION DATE
ACTIVITY
GOAL
STATUS / COMMENTS
CONSULTATION WITH
MARKET
BRS FOR NOMINATIONS
Draft BRS published by ENTSOG on 2 February 2014 for Public Consultation
Public Consultation on Draft BRS from 3 February – 14 March 2014
Finalise the Business Requirements Specifications for Nomination and Matching Procedures based on the Balancing Network Code
Amendment of BRS foreseen for Q1 2015
MONITORING AND REVIEWS RELATED TO THE BAL NC NETWORK CODE SUBMISSION (TAR NC)
Assess implementation plans of TSOs and NRAs for BAL NC
Implementation report published jointly by ENTSOG and ACER on 22 October 2014 TAR NC was submitted to ACER on 26 December 2014 – Auction calendar 2014 / 2015 published in 01 /2014 – CAM roadmap published in 10 / 2014 – Booking platform report published in 11 / 2014 Published in ENTSOG Annual Report on 2013
Consultation with TSOs and ACER
Follow up on implementation plans requested by Madrid Forum
Develop network code proposal
ACER, EC, TSOs, Stakeholders
TAR NC proposal scheduled for Comitology proceeding in 2015
IMPLEMENTATION ACTIVITIES CAM NC
ACER, TSOs, Market Stakeholders
– Road Map update foreseen October 2015 – Auction Calendar 2015 / 2016 scheduled for publication January 2015
CAM Road Map including list of Interconnection Points (IPs) where CAM NC is applied, Booking platform report, auction calendar 2014 / 2015
CMP IMPLEMENTATION
Collect data and survey ENTSOG members for status of CMP implementation Establish a market-based process to satisfy all economically reasonable and technically feasible demand for capacity via an amend- ment of the CAM NC and a chapter in the TAR NC
ACER, TSOs
Next publication of report in ENTSOG Annual Report 2014
INCREMENTAL CAPACITY (INC)
Incremental Proposal was submit- ted to ACER on 26 December 2014
TSOs, ACER, EC, Market Stakeholders
All over the year stakeholder interaction took place. ENTSOG organised a series of public work- shops and talks with ACER and EC Incremental Proposal is scheduled for Comitology proceeding in 2015 Stakeholders workshops and public consultation planned, scheduled to finish in April 2015
BUSINESS REQUIRE- MENT SPECIFICATION FOR CAM/CMP
Develop BRS to support CAM NC and CMP implementation by the TSOs
Throughout 2014 TSOs have devel- oped documentation which will be consulted in 2015
TSOs
16 |